Mathematics, 04.11.2020 03:30 davidoj13

A 12-person road crew is scheduled to finish repairing a highway in 6 days. On the morning of the third day, several new workers join the crew and, together, they complete the remaining repairs in 2 days. How many new workers joined the crew? I know someone posted this question already, but both answers were wrong.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 23:00
Bobs burgers bam has a special deal of 4 hamburgers for $6. at that rate, how much should it cost to buy 3 hamburgers?
Answers: 1
question
Mathematics, 22.06.2019 02:30
There are three grizzly bears in the city zoo. yogi weighs 400.5 pounds, winnie weighs 560.35 pounds, and nyla weighs 628.29 pounds. what is the average weight of the three bears? (hint: what do they weigh all together? ) a. 502.97 pounds c. 604.38 pounds b. 529.71 pounds d. 794.57 pounds
Answers: 1
question
Mathematics, 22.06.2019 05:30
Graph the linear equation. find threepoints that solve the equation, then ploton the graph.-x-3y=-6
Answers: 2
question
Mathematics, 22.06.2019 05:30
5of the first 50 shoppers at a grocery store buy apples. how many shoppers can the store manager expect to check out before 25 customers buy applesa.) 100b.)150c.)200d.)250
Answers: 2
You know the right answer?
A 12-person road crew is scheduled to finish repairing a highway in 6 days. On the morning of the th...
Questions
question
Mathematics, 25.04.2021 21:40
question
Mathematics, 25.04.2021 21:40
question
English, 25.04.2021 21:40
question
Mathematics, 25.04.2021 21:40
question
Mathematics, 25.04.2021 21:40
Questions on the website: 13722362