5. The number of days to complete research is inversely proportional to the number of researchers who are working. The research takes 125 days to complete it 5 people
work on it. Find how many people are needed to complete the research in 25 days?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:40
Will gve pints stars and brainliest
Answers: 1
question
Mathematics, 21.06.2019 21:10
Consider circle o, where and . m∠bpd °. °.
Answers: 3
question
Mathematics, 21.06.2019 21:30
Scott’s bank account showed a balance of $750 on sunday. during the next five days, he made one deposit of $140 and numerous withdrawals of $180 each. let x represent the number of withdrawals that scott made. write an inequality that can be used to find the maximum number of withdrawals that scott could have made and maintain a balance of at least $100. do not use a dollar sign ($) in your response.
Answers: 1
question
Mathematics, 21.06.2019 23:30
Answer each of the questions for the following diagram: 1. what type of angles are these? 2. solve for x. what does x equal? 3. what is the measure of the angles?
Answers: 1
You know the right answer?
5. The number of days to complete research is inversely proportional to the number of researchers w...
Questions
question
Physics, 21.06.2021 06:20
question
Computers and Technology, 21.06.2021 06:30
Questions on the website: 13722360