A can do a piece of work in 20 days and B can do it in 12 days, B work for 9 days, in how many days A alone can do the work

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Click on the graphic until you find the right quotient. (36xa - 30xb) ÷ (-6x2)
Answers: 3
question
Mathematics, 21.06.2019 18:00
Don't know how to find x given these segment lengths
Answers: 1
question
Mathematics, 21.06.2019 19:30
Solve the following simultaneous equation by using an algebraic method (either substitution or elimination) 2x + 3y=-4 4x-y=11
Answers: 1
question
Mathematics, 21.06.2019 22:10
Use the spider tool located on page 1 of this activity to draw a 12-pointed star for the new logo. (hint: if the spider rotates 360 degrees -- or 720 degrees or 1080 degrees -- she will be facing in the same direction in which she started. when the spider is done drawing, you want her to be facing in the same direction in which she started. she'll be making 12 rotations, all the same size, so each rotation must be some multiple of 360/12 = 30 degrees.) urgently. been stuck on this problem for around 45 minutes now.! it should be easy if you're smart enough
Answers: 3
You know the right answer?
A can do a piece of work in 20 days and B can do it in 12 days, B work for 9 days, in how many days...
Questions
Questions on the website: 13722367