(i) You are the cost Engineer for a construction company in charge of building a new bridge. The construction company will be penalized each day of delay in
construction for bridge. The penalty will be $4500 for the first day and will increase
by $12000 for each following day. Based on its budget, the company can afford to
pay a maximum of $ 155000 toward penalty. By modelling this as an arithmetic
progression, find the maximum number of days by which the completion of work can
be delayed.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 18:50
Which of the following values cannot be probabilities? 0.08, 5 divided by 3, startroot 2 endroot, negative 0.59, 1, 0, 1.44, 3 divided by 5 select all the values that cannot be probabilities. a. five thirds b. 1.44 c. 1 d. startroot 2 endroot e. three fifths f. 0.08 g. 0 h. negative 0.59
Answers: 2
question
Mathematics, 21.06.2019 19:20
What is x3+3x2−16x−48 divided by x−1?
Answers: 1
question
Mathematics, 21.06.2019 23:10
Point s lies between points r and t on . if rt is 10 centimeters long, what is st? 2 centimeters 4 centimeters 6 centimeters 8 centimeters
Answers: 2
question
Mathematics, 22.06.2019 00:00
Which is a logical conclusion based on the given information? a. figure abcd is a rhombus by the definition of a rhombus. b. segment ac is congruent to segment dc by cpctc. c. angle acb is congruent to angle adc by the angle-side-angle theorem. d. triangle acd is congruent to triangle cab by the hypotenuse-leg theorem.
Answers: 1
You know the right answer?
(i) You are the cost Engineer for a construction company in charge of building a new bridge. The co...
Questions
question
Social Studies, 14.01.2020 01:31
question
Mathematics, 14.01.2020 01:31
Questions on the website: 13722362