Activity D on a CPM network has predecessors B and C: and has successor F. D has duration 6. B's earliest finish is 18: while C's is 20. F's late start is 26. Which of the following is definitely true? a. D is critical and has zero slack.
b. B is a critical activity.
c. F is critical and has zero slack.
d. D has no slack but is not critical.
e. C is completed before B.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 20.06.2019 18:04
Atriangle has sides with lengths of 10 yards, 13 yards, and 18 yards. is it a right triangle?
Answers: 1
question
Mathematics, 21.06.2019 19:10
What is the quotient? x+5/ 3x²+4x+5 © 3x2 – 11 + x + s 3x – 11 + 60 x + 5 o 3x2 - 11 - 50 x + 5 3x – 11 - - x + 5
Answers: 3
question
Mathematics, 21.06.2019 19:30
Koji is installing a rectangular window in an office building. the window is 823 feet wide and 534 feet high. the formula for the area of a rectangle is a=bh. what is the area of the window? enter your answer as a mixed number in simplest form in the box. $$ ft2
Answers: 1
question
Mathematics, 21.06.2019 21:00
Tessa bought stock in a restaurant for $253.00. her stock is now worth $333.96. what is the percentage increase of the value of tessa's stock? a.) 81% b.) 32% c.) 24% d.) 76%
Answers: 1
You know the right answer?
Activity D on a CPM network has predecessors B and C: and has successor F. D has duration 6. B's ear...
Questions
question
Mathematics, 18.10.2020 16:01
question
Mathematics, 18.10.2020 16:01
question
Mathematics, 18.10.2020 16:01
Questions on the website: 13722362