Hayden is a manager at a landscaping company. he has 3 workers to
landscape an entire park, c...
Mathematics, 24.08.2019 03:30 Dalmcdan01
Hayden is a manager at a landscaping company. he has 3 workers to
landscape an entire park, cody, kaitlyn, and joseph. cody can complete
the project in 8 hours. kaitlyn can complete the project in 6 hours.
joseph is new, so no one knows how long it will take him.
hayden
assigns all of them to complete the park together. explain to hayden
how this project can tell him how long it would take joseph to complete
the project if he worked by himself. use complete sentences.
Answers: 1
Mathematics, 21.06.2019 20:00
The distribution of the amount of money spent by students for textbooks in a semester is approximately normal in shape with a mean of $235 and a standard deviation of $20. according to the standard deviation rule, how much did almost all (99.7%) of the students spend on textbooks in a semester?
Answers: 2
Mathematics, 21.06.2019 23:00
Which equation shows y= 3 4 x− 5 2 in standard form? a 4x−3y=10 b 3x−4y=10 c 3x−4y=−10 d 4x−3y=−10
Answers: 1
Mathematics, 28.05.2020 08:57
Mathematics, 28.05.2020 08:57
Biology, 28.05.2020 08:57
Law, 28.05.2020 08:57
History, 28.05.2020 08:57
Mathematics, 28.05.2020 08:57
Mathematics, 28.05.2020 08:57
Business, 28.05.2020 08:57
Mathematics, 28.05.2020 08:57
Mathematics, 28.05.2020 08:57
History, 28.05.2020 08:57
Biology, 28.05.2020 08:57
Mathematics, 28.05.2020 08:57
Mathematics, 28.05.2020 08:57
Mathematics, 28.05.2020 08:57