A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. 1) Draw the project network. Complete the project schedule
2) can they complete the project in 30 days?
3) Critical path is?
4) Which activity has the most slack?
Solve without using computer
Activity Time Immediate Predecessor
A. Find client 4
B. Write prospectus 2 A
C. Obtain approval from client and professor 3 B
D. Complete programming 12 C
E. Do industry background research 10
F. Write final paper 6 D, E
G. Write oral report 5 D, E

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
What is the volume of a rectangular prism that is 120 centimeters by 2 meters by 1.5 meters in cubic meters?
Answers: 1
question
Mathematics, 22.06.2019 00:30
Astudent was asked to find the square of 7x+3. the student quickly wrote (7x+3)^3= 49x^2+9. identify the student's error and provide the correct answer.
Answers: 3
question
Mathematics, 22.06.2019 01:30
What is the equivalent fraction for the following fraction using 5 as the multiplier? 1/2
Answers: 2
question
Mathematics, 22.06.2019 02:00
Aculinary club earns $1360 from a dinner service. they sold 45 adult meals and 80 student meals. an adult meal costs twice as much as a student meal. what is the cost of an adult meal?
Answers: 2
You know the right answer?
A senior MIS design class project team has developed the following schedule of activities for their...
Questions
question
History, 25.07.2019 06:00
question
Mathematics, 25.07.2019 06:00
Questions on the website: 13722359