The following table provides a description for the project Z. Activity Duration Predecessor Cost to crash Max Days
by 1 day to Crash
A 5 - $ 300 1
B 3 - $ 100 1
C 4 A $ 100 1
D 3 A $ 200 2
E 4 B $ 400 3
F 2 D, E $ 500 2
G 4 E $ 300 3
H 3 C $ 100 2
A. What is the critical path of this project?
The following table provides a description for the project Z.
Activity/ Duration/ Predecessor/ Cost to crash Max Days
by 1 day/ to Crash
A 5 - $ 300 1
B 3 - $ 100 1
C 4 A $ 100 1
D 3 A $ 200 2
E 4 B $ 400 3
F 2 D, E $ 500 2
G 4 E $ 300 3
H 3 C $ 100 2
B. What is the duration of this project?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 21:10
Given: lines a and b are parallel and line c is a transversal. prove: 2 is supplementary to 8 what is the missing reason in the proof? statement reason 1. a || b, is a transv 1. given 2. ∠6 ≅ ∠2 2. ? 3. m∠6 = m∠2 3. def. of congruent 4. ∠6 is supp. to ∠8 4. def. of linear pair 5. ∠2 is supp. to ∠8 5. congruent supplements theorem corresponding angles theorem alternate interior angles theorem vertical angles theorem alternate exterior angles theorem
Answers: 3
question
Mathematics, 21.06.2019 23:20
Which equation can be solved to find x the measure of jk in the apex
Answers: 3
question
Mathematics, 22.06.2019 01:30
Find the vertex for the parabola given by the function ƒ(x) = −3x2 − 6x.
Answers: 2
question
Mathematics, 22.06.2019 02:00
15 oranges weigh 3.75 kilograms (kg). if each orange weighs approximately the same, approximately how much does each orange weigh?
Answers: 2
You know the right answer?
The following table provides a description for the project Z. Activity Duration Predecessor Cost to...
Questions
Questions on the website: 13722363