A roofer requires 15 hours to shingle a roof, while an apprentice requires 21 hours. Write
an equation that can be used to find the time in hours, t, it would take to shingle the roof if
both worked together. Solve the equation.

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
The diameter of a circular chip is doubled to use in a new board game. the area of the new chip will be
Answers: 2
question
Mathematics, 21.06.2019 18:00
A. 90 degrees b. 45 degrees c. 30 degrees d. 120 degrees
Answers: 2
question
Mathematics, 21.06.2019 19:00
Which of the expressions (on the photo document i inserted) together represent all solutions to the following equation? 8cos(12x)+4=-4 *the answer should be in degrees.* > i would like for someone to explain the process to find the solutions for this.
Answers: 2
question
Mathematics, 21.06.2019 20:40
Askate shop rents roller skates as shown on the table below. which graph and function models this situation?
Answers: 1
You know the right answer?
A roofer requires 15 hours to shingle a roof, while an apprentice requires 21 hours. Write
an...
Questions
question
Biology, 03.08.2019 13:30
question
Computers and Technology, 03.08.2019 13:30
Questions on the website: 13722361