An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time. If the activity variance is 12, what is the expected time?

A) About 8 days

B) About 9 days

C) About 10 days

D) About 11 days

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:50
Examine the two-step equation. − 7 4 + x 4 = 2 which property of operations allows you to add the same constant term to both sides? amultiplication property of equality bdivision property of equality caddition property of equality dsubtraction property of equality
Answers: 2
question
Mathematics, 21.06.2019 20:00
Put the equation in slope intercept form by solving for y
Answers: 2
question
Mathematics, 21.06.2019 22:00
Fatima plans to spend at least $15 and at most $20 dollars on sketch pads and pencils. if she buys 2 sketchpads, how many pemcils can she buy while staying in her price range? fatima can buy between and pencils. ? (type whole numbers. use ascending? order.)
Answers: 1
question
Mathematics, 22.06.2019 00:00
The letters g e o r g i a are placed in a bag . if you picked a card and knew it was a vowel , what is the probability that it is an a ?
Answers: 1
You know the right answer?
An activity has a pessimistic time that is four times as long as its most likely time and six times...
Questions
question
History, 02.02.2022 14:20
Questions on the website: 13722367