2. "In a job shop, effective capacity is only 50 percent of design capacity, and actual output is" 80 percent of effective output. What design capacity would be needed to achieve an actual output of eight jobs per week?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 19:00
Rob spent 25%, percent more time on his research project than he had planned. he spent an extra h hours on the project. which of the following expressions could represent the number of hours rob actually spent on the project? two answers
Answers: 1
question
Mathematics, 21.06.2019 19:30
If you could answer these your a life saver
Answers: 2
question
Mathematics, 21.06.2019 20:30
Kayaks rent for $35 per day. which expression can you use to find the cost in dollars of renting 3 kayaks for a day?
Answers: 1
question
Mathematics, 22.06.2019 00:10
Change negative exponents to positive, then solve
Answers: 1
You know the right answer?
2. "In a job shop, effective capacity is only 50 percent of design capacity, and actual output is" 8...
Questions
question
History, 04.08.2019 11:30
question
Mathematics, 04.08.2019 11:30
Questions on the website: 13722367