Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 work-days and a standard deviation of 10 work-days. The probability that the project will be completed within 185 work-days is

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
Phyllis and chen are saving money to go to a football game. each friend starts with some money and saves a specific amount each week. phyllis made a graph to show the total she has saved at the end of each week. chen wrote an equation to show the total, y, he has saved at the end of each week, x. y = 15x + 15 compare the amount that each friend has when both friends start saving. select the correct answer from the drop-down menu to complete the statement. phyllis starts with $ and chen starts with $
Answers: 1
question
Mathematics, 21.06.2019 18:00
Jacob signs up to work for 2 1/2 hours at the school carnival. if each work shift is 3/4 hour, how many shifts will jacob work? (i just want to double check : |, for anybody that responds! : )
Answers: 3
question
Mathematics, 21.06.2019 22:30
Line wx is parallel to line yz. if m
Answers: 3
question
Mathematics, 21.06.2019 23:00
Acaterpillar eats 1400\%1400% of its birth mass in one day. the caterpillar's birth mass is mm grams. which of the following expressions could represent the amount, in grams, the caterpillar eats in one day? \
Answers: 1
You know the right answer?
Completion time (from start to finish) of a building remodeling project is normally distributed with...
Questions
question
Mathematics, 04.12.2020 08:50
question
Mathematics, 04.12.2020 08:50
question
Arts, 04.12.2020 08:50
question
Mathematics, 04.12.2020 08:50
question
Mathematics, 04.12.2020 08:50
question
Engineering, 04.12.2020 08:50
question
English, 04.12.2020 08:50
Questions on the website: 13722367