A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results:

Observation 1 2 3 4 5
Time 84 76 80 84 76

What is the standard time for this task if the employee worked at a 25 percent faster pace than average and an allowance of 20 percent of the workday is used?

a. 80 seconds
b. 96 seconds
c. 125 seconds

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 23:00
Edger needs 6 cookies and 2 brownies for every 4 plates how many cookies and brownies does he need for 10 plates
Answers: 1
question
Mathematics, 22.06.2019 04:00
Me on this i beg you on this to answer!
Answers: 2
question
Mathematics, 22.06.2019 04:40
This assignment is past the original due date o this data is from a sample. calculate the mean, standard deviation, and variance 16.7 11.1 46.7 14.8 13.3 16.6 18.5 47.3 42,8 show the following answers to 2 decimal places. sample mean- sample standard deviation ( use the standard deviation above for your calculation.) sample variance ooops- now you discover that the data was actually from a population! so now you must give the population standard deviation.
Answers: 3
question
Mathematics, 22.06.2019 05:20
What is the recursive formula for this sequence . 10,14,18,22,26
Answers: 2
You know the right answer?
A methods and measurements analyst needs to develop a time standard for a certain task. In a prelimi...
Questions
question
Mathematics, 17.12.2020 01:30
question
Mathematics, 17.12.2020 01:30
question
History, 17.12.2020 01:30
question
Computers and Technology, 17.12.2020 01:30
question
Mathematics, 17.12.2020 01:30
Questions on the website: 13722367