An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day.

a) What are the minimum and maximum cycle times?
b) What range of output is theoretically possible for the line?
c) What is the minimum number of worksheets needed if the maximum output rate is to be sought?
d) What cycle time will provide an output rate of 125 units per day?
e) What output potential will result if the cycle time is (1) 9 minutes? and (2) 15 minutes?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 16:10
Which of the following graphs represents the function f(x) = 2^x
Answers: 2
question
Mathematics, 21.06.2019 20:30
Arectangle has a width of 5 cm and a length of 10 cm. if the width is increased by 3, how does the perimeter change?
Answers: 1
question
Mathematics, 21.06.2019 23:00
The architect's side view drawing of a saltbox-style house shows a post that supports the roof ridge. the support post is 8 ft tall. the distance from the front of the house to the support post is less than the distance from the post to the back of the house. how far from the front of the house is the support post positioned?
Answers: 1
question
Mathematics, 21.06.2019 23:30
Sally deposited money into a savings account paying 4% simple interest per year.the first year,she earned $75 in interest.how much interest will she earn during the following year?
Answers: 2
You know the right answer?
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total tim...
Questions
question
Mathematics, 19.07.2019 09:00
question
Mathematics, 19.07.2019 09:10
Questions on the website: 13722367