O determine how to crash activity times
a. normal activity costs and costs under maximum crashing must be known.
b. shortest times with crashing must be known.
c. realize that new paths may become critical.
d. All of the alternatives are true.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 20.06.2019 18:02
Explain the answer and how to do it
Answers: 1
question
Mathematics, 21.06.2019 19:00
To solve the system of equations below, pedro isolated the variable y in the first equation and then substituted it into the second equation. what was the resulting equation? { 5y=10x {x^2+y^2=36
Answers: 1
question
Mathematics, 21.06.2019 21:30
Which of the following disjunctions is true? 4 + 4 = 16 or 6 - 5 = 11 4 · 3 = 7 or 3 - 2 = 5 8 - 5 = 13 or 7 · 2 = 12 7 - 4 = 11 or 6 + 3 = 9
Answers: 1
question
Mathematics, 22.06.2019 01:30
In the figure below, m∠r is 60°, and m∠t is 120°. what is m∠q? a. 60° b. 30° c. 120° d. 54
Answers: 1
You know the right answer?
O determine how to crash activity times
a. normal activity costs and costs under maximum crash...
Questions
question
Mathematics, 28.03.2020 05:07
question
History, 28.03.2020 05:07
question
Mathematics, 28.03.2020 05:07
Questions on the website: 13722360