A contractor is hired to do stone work. She is preparing an estimate for a wall and gate. The job is expected to take 40 hours. She needs 2 workers which
are paid $12 per hour and 3 more which are paid $20 per hour. Materials are expected to cost $3,240. She wants a $500 profit. What will be the overall
cost of this stone work?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 21:00
The functions below show the amount of money bella and sweet t had saved after earning money for doing chores. which description best compares the two functions?
Answers: 1
question
Mathematics, 21.06.2019 23:30
Which two fractions are equivalent to 6/11? 6/22 and 18/33 12/22 and 18/33 12/22 and 18/22 3/5 and 6/10
Answers: 1
question
Mathematics, 22.06.2019 00:30
The length of a rectangle plus its width is 24 cm. the area is 143 square cm. what are the length and width of the rectangle?
Answers: 1
question
Mathematics, 22.06.2019 03:00
Which aspect of electronic commerce does the ftc regulate? a. encryption and transfer of data b. disposing of credit reports c. network security d. antivirus software updates
Answers: 1
You know the right answer?
Management
A contractor is hired to do stone work. She is preparing an estimate for a wall and...
Questions
question
Engineering, 16.10.2019 17:30
Questions on the website: 13722361