Mathematics, 28.02.2020 02:26 brianna8739

Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a 0.90 probability that the project will be completed before approximately day .
i.98
ii.108
iii.109
iv.115
v.118

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 20.06.2019 18:02
Anew fountain in the shape of a hexagon will have 6 sides of equal length. on a scale drawing, the coordinates of the vertices of the fountain are: (7.5,5), (11.5,2), (7.5,−1), (2.5,−1), (−1.5,2), and (2.5,5). how long is each side of the fountain?
Answers: 3
question
Mathematics, 21.06.2019 15:00
Use addition and subtraction to simplify the following polynomials. a. add polynomials: (3 – 4x + 8x^2) + (–6 + 2x – 5x^2) step 1: rewrite the polynomials without the parentheses. step 2: write the polynomial in descending order and use parentheses around like terms. step 3: add the like terms identified in step 2 to simplify the polynomial. b. subtract polynomials: (3x – 5 – 7x^2) – (–2 + 6x^2 – 5x) step 1: rewrite the polynomials without the parentheses. remember to multiply each term in the second parentheses by –1. show your work. step 2: write the polynomial in descending order and use parentheses around like terms. step 3: add the like terms identified in step 2 to simplify the polynomial.
Answers: 3
question
Mathematics, 21.06.2019 15:10
Solve the system by the elimination method. x + y - 6 = 0 x - y - 8 = 0 when you eliminate y , what is the resulting equation? 2x = -14 2x = 14 -2x = 14
Answers: 2
question
Mathematics, 21.06.2019 16:00
Write two subtraction equations that are equivalent to 5 + 12 = 17.
Answers: 2
You know the right answer?
Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a vari...
Questions
question
Mathematics, 26.03.2021 03:40
Questions on the website: 13722363