subject
Mathematics, 20.02.2020 07:42 ksteele1

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 224 days or more to complete?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
Which is the completely factored from of xy^3-x^3y
Answers: 3
question
Mathematics, 21.06.2019 17:50
Find the cosine function that is represented in the graph.
Answers: 1
question
Mathematics, 21.06.2019 22:30
Select all of the following expressions that are equal to 2.5.
Answers: 3
question
Mathematics, 22.06.2019 00:00
Plz answer asap! i will reward brainliest and 12 points for these three questions!take notice: these three questions are completely different! 1) what is the percentage of sugar in the syrup made of 10 kg of water and 4 kg of suugar? 2) what was the original price if after 10% discount it became $450? 3) at first a price was decreased by 12%, then it was disounted again by an additional 5%. what is the percent of the total discount? , and remeber i will award brainliest and 12 points!
Answers: 1
You know the right answer?
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the est...
Questions
question
Mathematics, 13.03.2021 03:30
question
Arts, 13.03.2021 03:30
question
Mathematics, 13.03.2021 03:30
question
Mathematics, 13.03.2021 03:30
Questions on the website: 13722359