Simplify (7 + 1)2 - (11 +32) + 4.
Ο
Ο Α. 59
Ο
Ο Β. -13
OC. 17
Ο...
Mathematics, 19.02.2020 19:58 andrew729
Simplify (7 + 1)2 - (11 +32) + 4.
Ο
Ο Α. 59
Ο
Ο Β. -13
OC. 17
Ο D. -3
Ο
Answers: 2
Mathematics, 21.06.2019 21:30
Using pert, adam munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4. a) what is the probability that the project will be completed in 17 months? b) what is the probability that the project will be completed in 20 months? c) what is the probability that the project will be completed in 23 months? d) what is the probability that the project will be completed in 25 months? e) what is the due date that yields a 95% chance of completion?
Answers: 3
Mathematics, 21.06.2019 23:00
In trapezoid abcd, ac is a diagonal and ∠abc≅∠acd. find ac if the lengths of the bases bc and ad are 12m and 27m respectively.
Answers: 3
Mathematics, 22.06.2019 00:00
Can someone me with this graph problem by the way i need to know the answers by today since this assignment is due ! !
Answers: 1
Mathematics, 22.06.2019 02:30
What is the slope-intercept form of a line that passes through points (2, 11) and (4, 17)? y=-3x-5 o y=3x-5 y=-3x+5 0y=3x+5
Answers: 2
Spanish, 22.04.2020 01:03
Biology, 22.04.2020 01:03
Advanced Placement (AP), 22.04.2020 01:04