A12-person construction crew is scheduled to finish repairing a highway in 6 days. on the morning of the 3rd day, several new workers joined the crew. together they completed the remaining job in 2 days. how many new workers joined the crew?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:40
Im gonna fail 7th grade selective breeding 1. creates offspring which are genetically identical to the parent 2. is the process of breeding only organisms with desirable traits 3. involves the removal of the nucleus of a cell 4. combines traits from organisms of different species
Answers: 2
question
Mathematics, 21.06.2019 18:30
Which expression is not a polynomial?
Answers: 2
question
Mathematics, 21.06.2019 19:00
John used linear combination to solve the system of equations shown. he did so by multiplying the first equation by -3 and the second equation by another number to eliminate the x-terms. what number did jonas multiply the second equation by? 4x-6y=23x+5y=11
Answers: 2
question
Mathematics, 21.06.2019 21:40
What is the inverse of the function f(x) = 2x + 1?
Answers: 3
You know the right answer?
A12-person construction crew is scheduled to finish repairing a highway in 6 days. on the morning of...
Questions
Questions on the website: 13722360