subject
Mathematics, 13.01.2020 21:31 lilpump3506

You have an annual demand of 494,000 units, inventory carrying costs of 25.8%, a unit cost of $127.22, and an ordering cost of $84.73. calculate q*.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 15:10
6x - 8 = 16 solve the following equation. then place the correct number in the box provided.
Answers: 2
question
Mathematics, 21.06.2019 17:00
Describe what moves you could use to create the transformation of the original image shown at right
Answers: 1
question
Mathematics, 21.06.2019 21:30
Noel is hoping to make a profit (in $) on the school play and has determined the function describing the profit to be f(t) = 8t – 2654, where t is the number of tickets sold. what does the number 8 tell you?
Answers: 1
question
Mathematics, 21.06.2019 21:30
Using pert, adam munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4. a) what is the probability that the project will be completed in 17 months? b) what is the probability that the project will be completed in 20 months? c) what is the probability that the project will be completed in 23 months? d) what is the probability that the project will be completed in 25 months? e) what is the due date that yields a 95% chance of completion?
Answers: 3
You know the right answer?
You have an annual demand of 494,000 units, inventory carrying costs of 25.8%, a unit cost of $127.2...
Questions
question
Mathematics, 01.02.2020 12:43
question
Mathematics, 01.02.2020 12:43
question
Social Studies, 01.02.2020 12:43
question
Mathematics, 01.02.2020 12:43
Questions on the website: 13722367