Consider the following work breakdown structure:
duration estimates days
activity precedes optimistic most likely pessimistic
start u, v - - -
u w 35 50 65
v w, x 28 40 52
w z 26 35 44
x y 28 40 52
y z 26 29 38
z end 36 60 84
what is the estimated expected (mean) time for project completion?
a. 135 days
b. 145 days
c. 170 days 1
d. 80 days
e. 255 days

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 20:00
For problems 29 - 31 the graph of a quadratic function y=ax^2 + bx + c is shown. tell whether the discriminant of ax^2 + bx + c = 0 is positive, negative, or zero.
Answers: 1
question
Mathematics, 21.06.2019 20:00
15 there is a line that includes the point 0,10 and has a slope of 7/4. what is it’s equation in slope intercept form
Answers: 1
question
Mathematics, 22.06.2019 04:30
Marcy is conducting a study regarding the amount of time students at her school spend talking to friends online. which group would give marcy the best results for her study?
Answers: 3
question
Mathematics, 22.06.2019 06:10
The diagram shows some steps in the construction of the inscribed circle of abc. which diagram shows the next step in the construction?
Answers: 3
You know the right answer?
Consider the following work breakdown structure:
duration estimates days
activity prece...
Questions
question
English, 21.02.2021 23:40
question
Social Studies, 21.02.2021 23:50
Questions on the website: 13722362