Analysis of a pert problem shows the estimated time for the critical path to be 108 days with a variance of 64. there is a .90 probability that the project will be completed before approximately day
98
108
109
115
118

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 12:40
For what values of b will f(x)= logbx be a decreasing function? (16 )
Answers: 1
question
Mathematics, 21.06.2019 18:00
How do you solve a question like this?
Answers: 2
question
Mathematics, 21.06.2019 20:00
Elizabeth is using a sample to study american alligators. she plots the lengths of their tails against their total lengths to find the relationship between the two attributes. which point is an outlier in this data set?
Answers: 1
question
Mathematics, 21.06.2019 22:40
Find the missing factor. write your answer inexponential form.9^2=9^4×
Answers: 1
You know the right answer?
Analysis of a pert problem shows the estimated time for the critical path to be 108 days with a vari...
Questions
question
Mathematics, 01.01.2020 21:31
Questions on the website: 13722363