Aproject has an expected completion time of 25 days. it is given that project completion time has a standard deviation of 2.645 days. what is the probability that this project will be completed less than 21 days and 12 hours?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Abcd is a parallelogram find the valuse of x
Answers: 1
question
Mathematics, 21.06.2019 18:30
Consider the function f(x)=-5x+3 what is f(-2)
Answers: 2
question
Mathematics, 21.06.2019 19:00
Stefano accidentally dropped his sunglasses off the edge of a canyon as he was looking down. the height, h(t), in meters (as it relates to sea level), of the sunglasses after t seconds, is shown in the table. during its descent, the pair of sunglasses passed by a climber in the canyon 6 seconds after stefano dropped them. to the nearest meter, what is difference in elevation between stefano and the climber? 166 meters 176 meters 230 meters 240 meters its b.176 i took the test 166 is wrong and 176 is correct
Answers: 1
question
Mathematics, 21.06.2019 23:00
Find the rate at which the water is now flowing from the tap give your answer cubic centimetres per second
Answers: 1
You know the right answer?
Aproject has an expected completion time of 25 days. it is given that project completion time has a...
Questions
question
Business, 06.01.2021 22:40
question
Mathematics, 06.01.2021 22:40
question
English, 06.01.2021 22:40
question
History, 06.01.2021 22:40
Questions on the website: 13722360