8men will take 10 days to build a wall 150 metres long. after the men had started working for 6 days, they were told that the wall needed to by lengthened by 45 metres. how many more men must be hired to complete the job on time?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 20.06.2019 18:02
Elijah brought a total of 16 pounds of peanuts and cashew nuts and paid $49.50. if peanuts cost $2.75 per pound and cashew nuts cost $3.25 per pound, how many pounds of cashew nuts did he buy?
Answers: 2
question
Mathematics, 21.06.2019 16:30
What are “like terms”? why can we only add like terms?
Answers: 1
question
Mathematics, 21.06.2019 23:30
Scenario: a rectangular plot of ground is 5 meters longer than it is wide. its area is 20,000 square meters. question: what equation will you find the dimensions? note: let w represent the width. options: w(w+5)=20,000 w^2=20,000+5 (w(w+5))/2=20,000 w+2(w+5)=20,000
Answers: 1
question
Mathematics, 22.06.2019 00:30
What is the geometric mean of 3 and 7? a) square root of 21 b) 2 square root of 6 c) 2 square root of 7 d) 21
Answers: 2
You know the right answer?
8men will take 10 days to build a wall 150 metres long. after the men had started working for 6 days...
Questions
question
English, 24.08.2019 04:30
question
Mathematics, 24.08.2019 04:30
Questions on the website: 13722367