Mathematics, 17.11.2019 21:31 meme2186

Two companies working together can clear a parcel of land in 30 hours. working alone, it would take company a 3 hours longer to clear the land than it would company b. how long would it take company b to clear the parcel of land alone? (round your answer to the nearest tenth.)

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 12:30
What is the value of 1/3x + 7x when x = 5
Answers: 1
question
Mathematics, 21.06.2019 18:30
What is the prime factorization of 230
Answers: 1
question
Mathematics, 21.06.2019 20:30
If g^-1(x) is the inverse of g (x) which statement must be true
Answers: 3
question
Mathematics, 21.06.2019 21:00
Hurrya vegetable garden and a surrounding path are shaped like a square that together are 11ft wide. the path is 2ft wide if one bag of gravel covers 9 square feet how many bags are needed to cover the path
Answers: 1
You know the right answer?
Two companies working together can clear a parcel of land in 30 hours. working alone, it would take...
Questions
question
Mathematics, 17.01.2022 23:50
question
Mathematics, 18.01.2022 01:00
question
Mathematics, 18.01.2022 01:00
question
Mathematics, 18.01.2022 01:00
question
Mathematics, 18.01.2022 01:00
Questions on the website: 13722363