Mathematics, 12.11.2019 22:31 arturocarmena10
The observed average time in a direct time study was 2.40 min for a repetitive work cycle. the worker’s performance was rated at 110% on all cycles. the personal time, fatigue, and delay allowance for this work is 12%. determine (a) the normal time and (b) the standard time for the cycle.
Answers: 2
Mathematics, 21.06.2019 20:30
Find the nonpermissible replacement for binthis expression.b2/5b +5
Answers: 1
Mathematics, 21.06.2019 22:00
Given sin∅ = 1/3 and 0 < ∅ < π/2 ; find tan2∅ a. (4√2)/9 b. 9/7 c. (4√2)/7 d.7/9
Answers: 2
Mathematics, 21.06.2019 23:00
*segment an is an altitude of right ? abc with a right angle at a. if ab = 2root 5 in and nc = 1 in, find bn, an, ac.
Answers: 3
The observed average time in a direct time study was 2.40 min for a repetitive work cycle. the worke...
Mathematics, 09.04.2020 19:59
Mathematics, 09.04.2020 20:00
Mathematics, 09.04.2020 20:00
Mathematics, 09.04.2020 20:00
Mathematics, 09.04.2020 20:00
Chemistry, 09.04.2020 20:00
English, 09.04.2020 20:00
Biology, 09.04.2020 20:00