Provide an appropriate response. in order to efficiently bid on a contract, a contractor wants to be 95% confident that his error is less than two hours in estimating the average time it takes to install tile flooring. previous contracts indicate that the standard deviation is 4.5 hours. how large a sample must be selected?
a.19
b.4
c.5
d.20

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 13:00
Sal is tiling his entryway. the floor plan is drawn on a unit grid. each unit length represents 1 foot. tile costs $1.35 per square foot. how much will sal pay to tile his entryway? round your answer to the nearest cent.
Answers: 2
question
Mathematics, 21.06.2019 13:30
After two years, how much has been paid into interest?
Answers: 1
question
Mathematics, 21.06.2019 17:30
Write the fraction 9/50 as a decimal if needed round to the nearest hundredth
Answers: 2
question
Mathematics, 21.06.2019 19:00
Aplot of land has been surveyed for a new housing development with borders ab, bc, dc, and da. the plot of land is a right trapezoid with a height of 60 feet and an opposite leg length of 65 feet
Answers: 1
You know the right answer?
Provide an appropriate response. in order to efficiently bid on a contract, a contractor wants to be...
Questions
question
Geography, 11.07.2019 18:30
Questions on the website: 13722367