You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. the probability that the project will be completed in 33 days or less is equal to (2 decimal accuracy)
a. 0.73 b. 0.55.c. 0.12 d. 0.27 e. 0.60.
Answers: 2
Mathematics, 21.06.2019 21:00
Abakery recorded the number of muffins and bagels it sold for a seven day period. for the data presented, what does the value of 51 summarize? a) mean of bagels b) mean of muffins c) range of bagels d) range of muffins sample # 1 2 3 4 5 6 7 muffins 61 20 32 58 62 61 56 bagels 34 45 43 42 46 72 75
Answers: 2
Mathematics, 21.06.2019 21:00
Two cars which are 40 miles apart start moving simultaneously in the same direction with constant speeds. if the speed of the car which is behind is 56 mph and the speed of the other car is 48 mph, how many hours will it take for the car which is behind to catch up the car ahead of it?
Answers: 2
Mathematics, 21.06.2019 22:00
Problem situation: caren is making rice and beans. she can spend no more than $10 on ingredients. she buys one bag of rice for $4.99. beans cost $0.74 per pound. how many pounds of beans, x, can she buy? inequality that represents this situation: 10≥4.99+0.74x drag each number to show if it is a solution to both the inequality and the problem situation, to the inequality only, or if it is not a solution.
Answers: 1
You have just used the network planning model and found the critical path length is 30 days and the...
Physics, 03.11.2019 23:31
English, 03.11.2019 23:31
English, 03.11.2019 23:31
Mathematics, 03.11.2019 23:31
Mathematics, 03.11.2019 23:31
Mathematics, 03.11.2019 23:31
Mathematics, 03.11.2019 23:31
History, 03.11.2019 23:31