Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks. what is the probability that the project will take anywhere between 60 and 65 weeks to complete? (round to two decimals.)
Answers: 3
Mathematics, 21.06.2019 21:00
Askateboard ramp is in the shape of a right triangle what is the height of the ramp
Answers: 3
Mathematics, 22.06.2019 00:00
Yvaries inversely as x. y =12 when x=5. find y when x=4
Answers: 2
Mathematics, 22.06.2019 00:00
Apolygon is shown on the graph: a polygon is shown on the coordinate plane. vertices are located at 3 comma 5, 1 comma 3, 1 comma 1, 2 comma 0, 4 comma 0, 5 comma 1, and 5 comma 3. what effect will a translation 3 units down and 2 units left have on the polygon? be sure to address how it could impact the angles, side lengths, and congruency between the original pre-image and the image. xd i need