Aproject whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)? 98 112 120 124 220

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:00
The fence around a quadrilateral-shaped pasture is 3a^2+15a+9 long. three sides of the fence have the following lengths: 5a, 10a-2, a^2-7. what is the length of the fourth side of the fence?
Answers: 1
question
Mathematics, 21.06.2019 21:00
The? half-life of a radioactive substance is 20 years. if you start with some amount of this? substance, what fraction will remain in 120 ? years
Answers: 1
question
Mathematics, 21.06.2019 22:00
Prove sin2a + cos2a - 1 / sin2a + cos2a + 1 = 1 - tana / 1 + cota
Answers: 2
question
Mathematics, 22.06.2019 01:00
Triangles abd and ace are similar right triangles. witch ratio best explains why the slope of ab is the same as the slope of ac?
Answers: 2
You know the right answer?
Aproject whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chan...
Questions
question
Mathematics, 31.10.2019 22:31
question
Mathematics, 31.10.2019 22:31
question
History, 31.10.2019 22:31
Questions on the website: 13722363