There are two machines that produce aluminum cans. the newer machine can produce 4200 cans in 210 minutes. it takes the older machine 280 minutes to produce that many cans. if the two machines work together, how long will it take them to produce 4200 cans?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:10
A) if $50000 is invested in a bank account that pays 9.3% of interest compounded on a six-monthly basis, how much money will be in the account after 3 and 12 years? b) if matusalen's father had put $2.0 in the bank when he was born and there, how long would matusalen have had to his death (969 years later) if the interest was 7% per year composed each month and weekly?
Answers: 1
question
Mathematics, 21.06.2019 20:50
Amanda went into the grocery business starting with five stores. after one year, she opened two more stores. after two years, she opened two more stores than the previous year. if amanda expands her grocery business following the same pattern, which of the following graphs represents the number of stores she will own over time?
Answers: 3
question
Mathematics, 21.06.2019 22:00
Describe how you can act financially responsible.
Answers: 1
question
Mathematics, 21.06.2019 22:00
[tex]5 \times1 \frac{12}{13} [/tex] me
Answers: 1
You know the right answer?
There are two machines that produce aluminum cans. the newer machine can produce 4200 cans in 210 mi...
Questions
question
Computers and Technology, 23.05.2020 01:00
question
Mathematics, 23.05.2020 01:00
question
Mathematics, 23.05.2020 01:00
Questions on the website: 13722363