Engineering, 10.12.2021 19:20 Kassi07

If you are representing the owner/engineer, and during the bidding phase of a project, a bidder telephones your office calling attention to what the bidder believes to be an error, and makes a request for clarification or correction, you should: . A. check out the reported error while still on the telephone, give the caller the corrected data orally, then send an addenda to everyone e1se .
B. deny that an error exists and tell the caller to bid the work as it was specified and make his or her own interpretations.
C. take all of the information from the caller, then advise him or her to bid the job as it was originally specified unless an addenda is issued, and that if an error was in fact discovered, it will be corrected by addenda which will be mailed to all bidders.
D. try to be as helpful as possible by checking with the original designer; then, if an error is noted, give the caller the correct information, but do not go out of your way to inform others unless they call with the same question.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
The temperature of air decreases as it is compressed by an adiabatic compressor. a)- true b)- false
Answers: 2
question
Engineering, 04.07.2019 18:10
Abrake has a normal braking torque of 2.8 kip in and heat-dissipating cast-iron surfaces whose mass is 40 lbm. suppose a load is brought to rest in 8.0 s from an initial angular speed of 1600 rev/min using the normal braking torque; estimate the temperature rise of the heat dissipating surfaces.
Answers: 3
question
Engineering, 04.07.2019 18:10
Water at 55c flows across a flat plate whose surface temperature is held constant at 95c. if the temperature gradient at the plate's surface for a given value of x is 18 c/mm, find a) local heat transfer coefficient. b) heat flux
Answers: 3
question
Engineering, 04.07.2019 18:10
Which of the following controllers anticipates the future from the slope of errors over time? a)-proportional b)-on/off c)-integral d)-derivative.
Answers: 2
You know the right answer?
If you are representing the owner/engineer, and during the bidding phase of a project, a bidder tele...
Questions
question
Mathematics, 07.01.2020 01:31
question
Mathematics, 07.01.2020 01:31
question
History, 07.01.2020 01:31
Questions on the website: 13722363