1. What is the productivity rate using cycle time for the following information:
I
Type of Wo...
Engineering, 18.02.2021 03:50 devontemiles8868
1. What is the productivity rate using cycle time for the following information:
I
Type of Work β Hauling
Average Cycle Time β 35 Minutes
Truck Capacity β 25 Tons
Crew - One Driver
Productivity Factor - 0.85
System Efficiency β 55 Minutes
per
Hour
Answers: 2
Engineering, 04.07.2019 18:10
The higher the astm grain size number, the finer the gran is. a)-true b)-false
Answers: 2
Engineering, 04.07.2019 19:10
Aplate of dimensions 3 m x 3 m is placed 0.37 mm apart from a fixed plate. the plate requires a force of 2n to move at speed of 45 cm/s. evaluate the viscosity of the fluid in between the plates
Answers: 3
Engineering, 05.07.2019 19:10
Tech a says never use a water hose to clean up dust after a repair. tech b says never use a floor scrubber to clean up dust after repairs. who is correct?
Answers: 1
Engineering, 06.07.2019 03:10
An electrical kettle is made out of stainless steel,weighs two pounds (when empty) with a heating element that consumes 2 kw of electricity. assuming that the water and the kettle are at the same uniform temperature at any moment of time, calculate the shortest possible time to bring 2 quarts of water from room temperature to the onset of boiling.
Answers: 1