A PLC has a TON Timer block with 16-bit PV variable and maximum time base 1 sec. With this configuration, the maximum time the timer can handle is around 18.2 hours (assuming unsigned PV variable). It is required to turn on an output after 24 hours. One way to achieve the 24 hours is to combine the timer with a counter. Required:
Design a ladder logic program that turns on an output after 24 hours. For each timer you use, specify the time base and preset values. For each counter you use, specify the preset value. You do not have to repeat the output action every 24 hours. In other words, your design does not have to repeat the pattern every 24 hours. Assume any missing information.

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Apump is used to circulate hot water in a home heating system. water enters the well-insulated pump operating at steady state at a rate of 0.42 gal/min. the inlet pressure and temperature are 14.7 lbf/in.2, and 180°f, respectively; at the exit the pressure is 60 lbf/in.2 the pump requires 1/15 hp of power input. water can be modeled as an incompressible substance with constant density of 60.58 lb/ft3 and constant specific heat of 1 btu/lb or. neglecting kinetic and potential energy effects, determine the temperature change, in °r, as the water flows through the pump.
Answers: 1
question
Engineering, 04.07.2019 18:10
Ifa component is made of two or more materials with different modulus of elasticity (e), it is called a composite member and we calculate the factor·n". mention the formula for calculating n". also, ifn> 1, explain what will happen to the 1. transformed.gi) ifn 1, what will happen to the material when transformed material when
Answers: 1
question
Engineering, 04.07.2019 18:20
Most leaks in reciprocating air compressors can be detected and minimized by: (clo4) a)-detecting leakage areas using ultrasonic acoustic detector. b)-tightening joints and connections c)-replacing faulty equipment d)-all of the given options
Answers: 2
question
Engineering, 04.07.2019 18:20
Inspection for bearing condition will include: (clo4) a)-color b)-smell c)-size d)-none of the above
Answers: 1
You know the right answer?
A PLC has a TON Timer block with 16-bit PV variable and maximum time base 1 sec. With this configura...
Questions
question
Mathematics, 12.11.2020 18:30
question
Mathematics, 12.11.2020 18:30
question
Mathematics, 12.11.2020 18:30
question
History, 12.11.2020 18:30
question
Mathematics, 12.11.2020 18:30
Questions on the website: 13722367