1- After the elapsing of 10 full days into the 14-day project duration, it is found that the update schedule indicates that a delay of 9 days has been experienced in the execution of Activity B and that a delay to the start of Activity D has consumed this activity’s “free float”. Clearly provide answers (numeric figures accompanied by clear explanations regarding the basis of the numeric figures) to the following:

a) What is the “now” projected total project duration and what drives this new figure

b) Explain the change (if any) to the total float of Activity L?

c) How much free and total floats can still be enjoyed by Activity D?

d) Given the delays described above, and provided that Activities C and F are shown to have been completed but with a joint consumption of 4 out of the 7 days of total float that were originally available to the C-F-K activity chain: (i) what interference (in days) to the scheduling of Activity K can be solely attributed to the completed execution of Activity B? (3 points) And, (ii) what total float can still be enjoyed by Activity K?

2- Given the delay reported to have taken place to the start of Activity D and the flexibility (if any) being now enjoyed (currently under the updated schedule), please argue what circumstances would warrant that the contractor’s PM, in consultation with his site-management subordinates, considers adopting a revised method of work, crew assignment (no. of crews), and/or work-shift schedule, and whether any one or more of these circumstances is/are evident in the updated schedule in connection with the scheduling results newly computed for D.

3- Assume the total duration for the project under study is expressed in months, totaling 14 months, on the basis of adopting a DBB project delivery approach. When will an estimate of this overall duration have been first made? And, what kind of control will be needed regarding this 14-month duration if the owner decides to switch to the “CM at Fee” approach at the point of time when the design phase has reached around 30% completion?

ansver
Answers: 2

Another question on Engineering

question
Engineering, 03.07.2019 15:10
Ahouse has the following electrical appliance usage (1) single 40w lamp used for 4 hours per day (2) single 60w fan used for 12 hours per day (3) single 200w refrigerator that runs 24 hours per day with compressor run 12 hours and off 12 hours find the solar power inverter size in watt with correction factor of 1.25.
Answers: 1
question
Engineering, 04.07.2019 16:10
The force on a cutting tool are 2600n vertically downward and 2100 horizontal. determine the resultant force acting on the tool and the angle at which it acts.
Answers: 1
question
Engineering, 04.07.2019 18:10
Air is to be cooled in the evaporator section of a refrigerator by passing it over a bank of 0.8-cm-outer-diameter and 0.4-m-long tubes inside which the refrigerant is evaporating at -20°c. air approaches the tube bank in the normal direction at 0°c and 1 atm with a mean velocity of 4 m/s. the tubes are arranged in-line with longitudinal and transverse pitches of sl- st 1.5 cm. there are 30 rows in the flow direction with 15 tubes in each row. determine (a) the refrigeration capacity of this system and (b) pressure drop across the tube bank. evaluate the air properties at an assumed mean temperature of -5°c and 1 atm. is this a good assumption?
Answers: 1
question
Engineering, 04.07.2019 18:10
Asingle-geared blanking press has a stroke of 200 mm and a rated capacity of 320 kn. a cam driven ram is assumed to be capable of delivering the full press load at constant force during the last 15 percent of a constant-velocity stroke. the camshaft has an average speed of 90 rev/min and is geared to the flywheel shaft at a 6: 1 ratio. the total work done is to include an allowance of 16 percent for friction a) estimate the maximum energy fluctuation b) find the rim weight for an effective diameter of 1.2 m and a coefficient of speed fluctuation of 0.10
Answers: 1
You know the right answer?
1- After the elapsing of 10 full days into the 14-day project duration, it is found that the update...
Questions
question
Mathematics, 15.01.2020 10:31
question
Mathematics, 15.01.2020 10:31
Questions on the website: 13722367