Sheet-metal blanks are loaded into a stamping operation by an industrial robot. Loading time is 15 sec. Actuating the OBI press takes 6 sec, including part ejection. The completed parts are dropped by gravity into a container. The cost rate of the press is $54/hr, which includes the cost rate of the robot. The sampling die cost $36,000 and is expected to produce a total of 80,000 stampings during its life. Batch quantity is 1,500 parts. Time to set up the press before production is 15 min. Assume availability = 100%, scrap rate = 0%. Determine

(a) time to complete the batch,
(b) average production rate, and
(c) cost per piece of the unit operation.

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
During a steady flow process, the change of energy with respect to time is zero. a)- true b)- false
Answers: 2
question
Engineering, 04.07.2019 18:10
The drive force for diffusion is 7 fick's first law can be used to solve the non-steady state diffusion. a)-true b)-false
Answers: 1
question
Engineering, 04.07.2019 18:10
Which of the following controllers anticipates the future from the slope of errors over time? a)-proportional b)-on/off c)-integral d)-derivative.
Answers: 2
question
Engineering, 04.07.2019 18:10
Machinery that is a key part of the process and without which the plant or process cannot function is classifed as: (clo4) a)-critical machinery b)-essential machinery c)-general purpose machinery d)-none of the specified options.
Answers: 1
You know the right answer?
Sheet-metal blanks are loaded into a stamping operation by an industrial robot. Loading time is 15 s...
Questions
question
Mathematics, 18.02.2021 23:40
question
Business, 18.02.2021 23:40
question
English, 18.02.2021 23:40
question
Advanced Placement (AP), 18.02.2021 23:40
Questions on the website: 13722363