Q1) An engineer is considering the 4 machines below for laboratory railway track testing. Using present worth analysis, which machine should be selected? MARR is 8% per year.
Estimates Machine A Machine B Machine C Machine D
Initial cost, $ -144,000 -130,000 -155,000 -94,000
AOC, $/year -10,000 -11,100 -15,000 -1,000
Salvage value, $ 2,500 0 5,000 4,400
Life, years 3 6 3 6

ansver
Answers: 2

Another question on Engineering

question
Engineering, 03.07.2019 14:10
Line joining liquid phase with liquid and solid phase mixture is known as: a) liquidus b) solidus c) tie line d) none of the mentioned
Answers: 2
question
Engineering, 04.07.2019 18:10
The higher the astm grain-size number, the coarser the grain is. a)-true b)-false
Answers: 3
question
Engineering, 04.07.2019 18:10
Which one from below is not one of the reasons of planning failures? (clo3) a)-planner is careless. b-planner spend less time in the field but more time on the desk c)-planner is not qualified d)-planner does not have sufficient time to properly plan
Answers: 3
question
Engineering, 04.07.2019 18:20
Water vapor initially at 10 bar and 400 °c is contained within a piston-cylinder assembly. the water lost heat to the surrounding according to isochoric (iso-volumetric) process until its temperature is 150 °c. the water is then condensed isothermally to saturated liquid. for the water as a system, calculate the work in kj/kg
Answers: 2
You know the right answer?
Q1) An engineer is considering the 4 machines below for laboratory railway track testing. Using pres...
Questions
Questions on the website: 13722367