Engineering, 07.03.2020 17:42 jaylenmiller437

The following data for the activities of a project are available: ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 6 B - 4 C - 7 D A, B,C 5 E A, B,C 6 F D 9 G E 4 H F, G 8 I F, G 6 J H 7 Required: i. Draw the network, number the nodes, find the project completion time and calculate total, free and independent floats for the activities ii. When the activity duration of G is doubled, identify the critical path

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Water in a partially filled large tank is to be supplied to the roof top, which is 8 m above the water level in the tank, through a 2.2-cm-internal-diameter pipe by maintaining a constant air pressure of 300 kpa (gage) in the tank. if the head loss in the piping is 2 m of water, determine the discharge rate of the supply of water to the roof top in liters per second.
Answers: 3
question
Engineering, 04.07.2019 18:20
Have a greater impact on maintenance productivity than any other support group. (clo5) a)-the top management b)-inventory and purchasing c)-sub-contracting d)-cmms
Answers: 2
question
Engineering, 04.07.2019 18:20
Steam enters a converging nozzle at 3.0 mpa and 500°c with a at 1.8 mpa. for a nozzle exit area of 32 cm2, determine the exit velocity, mass flow rate, and exit mach number if the nozzle: negligible velocity, and it exits (a) is isentropic (b) has an efficiency of 94 percent
Answers: 2
question
Engineering, 04.07.2019 18:20
How much power could a wind turbine produce if it had the following specifications? cp = 0.45 -d=1.2kg/m3 d=50m v 5m/s
Answers: 2
You know the right answer?
The following data for the activities of a project are available: ACTIVITY IMMEDIATE PREDECESSOR DUR...
Questions
question
Mathematics, 06.03.2020 19:41
question
Mathematics, 06.03.2020 19:41
question
Mathematics, 06.03.2020 19:41
Questions on the website: 13722360