At the start of the effective red at an intersection approach to a pretimed signal, vehicles begin to arrive at a rate of 800 veh/h for the first 40 seconds and 500 veh/h from then on. The approach has a saturation flow rate of 1200 veh/h and an effective green of 20 seconds, and the cycle length is 40 seconds.
1. What is the total vehicle delay two full cycles after the 800- veh/h arrival rate begins?

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:20
Air is compressed isentropically from an initial state of 300 k and 101 kpa to a final temperature of 1000 k. determine the final pressure using the following approaches: (a) approximate analysis (using properties at the average temperature) (b) exact analysis
Answers: 1
question
Engineering, 04.07.2019 19:10
Analyze the factors that influence the choice between the following pairs of processes to make the products indicated: i) sand casting versus die casting of an electric-motor housing ii) thread rolling versus machining of a bolt for high-strength application. (co3/c5)
Answers: 3
question
Engineering, 04.07.2019 19:20
Acircular pipe of 30mm outside diameter is placed in an airstream at 30 c and latm pressure. the air moves in cross flow over the pipe at 20 m/s, while the outer surface of the pipe is maintained at 110 c. what is the drag force exerted on the pipe per unit length? what is the rate of heat transfer from the pipe per unit length?
Answers: 1
question
Engineering, 06.07.2019 03:20
Explain in your own word the concept of a solid solution, in alloys, and how it can be created.
Answers: 3
You know the right answer?
At the start of the effective red at an intersection approach to a pretimed signal, vehicles begin t...
Questions
question
Mathematics, 30.11.2020 18:40
question
Social Studies, 30.11.2020 18:40
question
Mathematics, 30.11.2020 18:40
question
Mathematics, 30.11.2020 18:40
Questions on the website: 13722361