A mason requires 12 mason-hours per 100 ft2 for the bottom 4 ft of wall, and a hod carrier requires 14.5 helper hours to mix the mortar and carry mortar and brick to the masons. The masons lay the brick, square and tool the joints, and clean up at the end of the day. Wages for the mason and helper are $22.50 and $13.50 per hour. Find the cost per square foot.

ansver
Answers: 1

Another question on Engineering

question
Engineering, 03.07.2019 14:10
Line joining liquid phase with liquid and solid phase mixture is known as: a) liquidus b) solidus c) tie line d) none of the mentioned
Answers: 2
question
Engineering, 04.07.2019 18:10
The mass flow rate of the fluid remains constant in all steady flow process. a)- true b)- false
Answers: 1
question
Engineering, 04.07.2019 18:10
Refrigerant 134a enters an insulated compressor operating at steady state as saturated vapor at -26°c with a volumetric flow rate of 0.18 m3/s. refrigerant exits at 9 bar, 70°c. changes in kinetic and potential energy from inlet to exit can be ignored. determine the volumetric flow rate at the exit, in m3/s, and the compressor power, in kw.
Answers: 1
question
Engineering, 04.07.2019 18:10
Condition monitoring is a major component of. (clo4) a)- predictive maintenance. b)-preventive maintenance c)-proactive maintenance d)-reactive maintenance.
Answers: 1
You know the right answer?
A mason requires 12 mason-hours per 100 ft2 for the bottom 4 ft of wall, and a hod carrier requires...
Questions
question
Mathematics, 03.03.2020 22:46
question
Biology, 03.03.2020 22:47
question
Social Studies, 03.03.2020 22:48
Questions on the website: 13722361