A120-cy/hr maximum output pump is used to place the concrete for a 200-cy slab. the concrete is supplied by 8-cy transit-mix trucks arriving at the site in 12-min intervals. the concrete batch plant is located 5 miles from the site. average truck speed is 30 mph. each transit-mix truck takes, on average, 10 min to discharge. the placement crew size is seven workers. average worker output is 5 cy of concrete per hr. if additional trucks are added the time to place the concrete will decrease

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 03:10
What precautions should you take to prevent injuries when dealing with heavy loads?
Answers: 1
question
Engineering, 04.07.2019 18:10
You are making beer. the first step is filling the glass carboy with the liquid wort. the internal diameter of the carboy is 15 in., and you wish to fill it up to a depth of 2 ft. if your wort is drawn from the kettle using a siphon process that flows at 3 gpm, how long will it take to fill?
Answers: 1
question
Engineering, 04.07.2019 18:10
Which of the following controllers anticipates the future from the slope of errors over time? a)-proportional b)-on/off c)-integral d)-derivative.
Answers: 2
question
Engineering, 04.07.2019 18:10
Which one from below is not one of the reasons of planning failures? (clo3) a)-planner is careless. b-planner spend less time in the field but more time on the desk c)-planner is not qualified d)-planner does not have sufficient time to properly plan
Answers: 3
You know the right answer?
A120-cy/hr maximum output pump is used to place the concrete for a 200-cy slab. the concrete is supp...
Questions
question
Mathematics, 10.09.2020 01:01
question
Mathematics, 10.09.2020 01:01
question
Mathematics, 10.09.2020 01:01
question
Mathematics, 10.09.2020 01:01
question
Chemistry, 10.09.2020 01:01
Questions on the website: 13722367