Engineering, 16.12.2019 19:31 kukisbae

Rough riders inc. manufactures jeans in the cutting and sewing process. jeans are manufactured in 50-jean batch sizes. the cutting time is 6 minutes per jean. the sewing time is 15 minutes per jean. it takes 5 minutes to move a batch of jeans from cutting to sewing.

a. compute the value-added, non-value-added, and total lead time of this process.

b. compute the value-added ratio. round to one decimal place.

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Draw the engineering stress-strain curve for (a) bcc; (b) fcc metals and mark important points.
Answers: 1
question
Engineering, 04.07.2019 18:10
Assuming compressible flow of air and that the measurements are done at flagstaff a pitot static tube that gives the difference of total and static pressure measures 0.35 m of mercury. what is the velocity of air? assume the temperature to be 300k. (submit your excel or matlab calculation sheet)
Answers: 1
question
Engineering, 04.07.2019 18:10
Items are similar to the free issue items, but their access is limited. (clo5) a)-bin stock items free issue b)-bin stock controlled issue c)-critical or insurance spares d)-rebuildable spares e)-consumables
Answers: 1
question
Engineering, 04.07.2019 18:10
Atmospheric air has a temperature (dry bulb) of 80° f and a wet bulb temperature of 60° f when the barometric pressure is 14.696 psia. determine the specific humidity, grains/lb dry air. a. 11.4 c. 55.8 d. 22.5 b. 44.1
Answers: 1
You know the right answer?
Rough riders inc. manufactures jeans in the cutting and sewing process. jeans are manufactured in 50...
Questions
Questions on the website: 13722360