Engineering, 11.12.2019 18:31 elias1019

A60 hz, 120 vrms generator is connected to a load that consumes 30kw of power at a power factor of cos(45) lagging. a capacitor is placed in parallel with the load to improve the power factor to cos(30) lagging. the reactive power without the capacitor is qold = 30kvar and with the capacitor qnew=17.32kvar. what is the value of c?

options:

-35 mf

-14.7 mf

-2.3 mf

0 mf

2.3 mf

14.7 mf

35 mf

ansver
Answers: 3

Another question on Engineering

question
Engineering, 04.07.2019 18:10
During a steady flow process, the change of energy with respect to time is zero. a)- true b)- false
Answers: 2
question
Engineering, 04.07.2019 18:20
Prove the equivalence between the two statements of the 2nd law of thermodynamics (i.e., a violation of one statement leads to the violatio the other statement)
Answers: 2
question
Engineering, 04.07.2019 19:20
Apure substance is a)-mixture of various chemical elements or compounds b)-substance that has a fixed chemical composition throughout c)-mixture that is homogeneous (such as air) d)-all the answers
Answers: 3
question
Engineering, 04.07.2019 19:20
Heat transfer by is the fastest mode of heat transfer that requires no intervening medium. a)-conduction b)-convection c)-radiation d)-conduction and convection
Answers: 1
You know the right answer?
A60 hz, 120 vrms generator is connected to a load that consumes 30kw of power at a power factor of c...
Questions
question
Mathematics, 26.11.2019 23:31
question
World Languages, 26.11.2019 23:31
question
Mathematics, 26.11.2019 23:31
Questions on the website: 13722359