A120 cy per hr maximum output pump is used to place the concrete for a 200 cy slab. the concrete is supplied by 8 cytransit-mix trucks arriving to the site on 12 min intervals. the concrete batch plant is located 5 miles from the site. averagetruck speed is 30 mph. each transit-mix truck takes, on average, 10 min to discharge. the placement crew size is 7 workers. average worker output is 5 cy of concrete per hr. (a) how long will the operation take? (b) how can the operation bereorganized more effectively?

ansver
Answers: 3

Another question on Engineering

question
Engineering, 03.07.2019 15:10
Two flowing streams of argon gas are adiabatically mixed to form a single flow/stream. one stream is 1.5 kg/s at 400 kpa and 200 c while the second stream is 2kg/s at 500 kpa and 100 ? . it is stated that the exit state of the mixed single flow of argon gas is 150 c and 300 kpa. assuming there is no work output or input during the mixing process, does this process violate either the first or the second law or both? explain and state all your assumptions.
Answers: 1
question
Engineering, 04.07.2019 18:10
Fluids at rest possess no flow energy. a)- true b)- false
Answers: 3
question
Engineering, 04.07.2019 18:10
Aturning operation is performed with following conditions: rake angle of 12°, a feed of 0.35 mm/rev, and a depth of cut of 1.1 mm. the work piece is aluminum alloy 6061 with t6 heat treatment (a16061-t6). the resultant chip thickness was measured to be 1.0 mm. estimate the cutting force, fc. use shear stress of 207 mpa and coefficient of friction on the tool face of 0.6.
Answers: 1
question
Engineering, 04.07.2019 19:10
The sum of the normal stresses does not change as the stress state rotates through an angle. a)-trune b)- false
Answers: 2
You know the right answer?
A120 cy per hr maximum output pump is used to place the concrete for a 200 cy slab. the concrete is...
Questions
question
English, 25.09.2019 05:30
Questions on the website: 13722363