Bill, a project manager, wants to hire external resources. What step should Bill take before hiring external resources? A.
verify the resources identified by experts
B.
review the project scope and task list
C.
gather information from previous and similar project files
D.
examine the adequacy of internal resources

The answer is D.) examine the adequacy of internal resources

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 16:00
Why should characters such as / \ " ' * ; - ? [ ] ( ) ~ ! $ { } < > # @ & | space, tab, and newline be avoided in file names?
Answers: 2
question
Computers and Technology, 22.06.2019 23:00
Which type of tab stop is most for weights and measurements?
Answers: 1
question
Computers and Technology, 24.06.2019 05:30
If you combine two cells into one, what action are you performing? a.  adding a new row or column      b.  splitting the cells      c.  removing a new row or column      d.  merging the cells
Answers: 2
question
Computers and Technology, 24.06.2019 06:30
For which utilities, if any, does the landlord pay?
Answers: 2
You know the right answer?
Bill, a project manager, wants to hire external resources. What step should Bill take before hiring...
Questions
Questions on the website: 13722363