subject

A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 16:50
3(c). is the following command correct? if not, correct the syntax and explain your answers. you can just rewrite/correct only the wrong parts. (4) select p#, city, zipcode, count(*) from client c, property p, viewing v where c.c# = v.c# and v.p# = p.p# group by p#, city having count(*) > 3;
Answers: 1
question
Computers and Technology, 22.06.2019 10:30
Choose the best explanation for the following statement communication is symbolic
Answers: 3
question
Computers and Technology, 23.06.2019 09:30
You wanted to look up information about alzheimer's, but you were unsure if it was spelled "alsheimer's" or "alzheimer's." which advanced search strategy would be useful? a) a boolean search b) using a wild card in your search c) trying different search engines d) doing a search for "alsheimer's not alzheimer's" asap. ill give brainlist.
Answers: 1
question
Computers and Technology, 23.06.2019 11:00
What are the possible consequences of computer hacking? what is computer piracy? describe some examples. what are the effects of computer piracy? what are the possible consequences of computer piracy? what is intentional virus setting? describe some examples. what are the effects of intentional virus setting? what are the possible consequences of intentional virus setting? what is invasion of privacy? describe some examples. what are the effects of invasion of privacy? what are the possible consequences of invasion of privacy? what is an acceptable use policy and what is the purpose of the acceptable use policy what is intellectual property and how can you use it?
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Mathematics, 18.06.2021 07:10
question
Mathematics, 18.06.2021 07:10
question
Mathematics, 18.06.2021 07:10
question
History, 18.06.2021 07:10
question
Mathematics, 18.06.2021 07:10
Questions on the website: 13722359