A project consists of 8 activities. The activity completion times and the precedence relationships are as follows:
Activity. Completion time Days. immediate predecessor activities.
A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F
1. Draw the network diagram using AON model notations:
2. What is the critical path?
3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.
4. What is the minimum time to complete the projects?
Please answer and thank you
Answers: 2
Computers and Technology, 22.06.2019 05:10
Read the code below. what will the computer print if the input for year_variable is 1700? if year_variable == 1776: print("your answer is correct. the declaration of independence was signed in “year_variable”.") elif year_variable < 1776: compute_variable = 1776 - year_variable. print("add “compute_variable“ years to your answer for the correct answer.") elif year_variable > 1776: compute_variable = year_variable - 1776 print("subtract “compute_variable” years from your answer for the correct answer.")
Answers: 1
Computers and Technology, 22.06.2019 11:00
You receive an email from an impressive-sounding stranger, professor alexander rothschild renard iii, president of the american institute for scientific political statesmen. he urges you to vote for his presidential candidate choice. this social media red flag is known as
Answers: 1
Computers and Technology, 24.06.2019 15:30
How do i change the size of my bookmarks in my bookmarks bar in google chrome? ? plz hlp me
Answers: 2
Computers and Technology, 25.06.2019 03:30
Which task should happen during the planning stage of a project
Answers: 2
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Mathematics, 18.06.2020 01:57
Mathematics, 18.06.2020 01:57
Mathematics, 18.06.2020 01:57
Mathematics, 18.06.2020 01:57
Mathematics, 18.06.2020 01:57
Mathematics, 18.06.2020 01:57
Mathematics, 18.06.2020 01:57