subject

A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

Please answer fast

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 22.06.2019 19:50
Write a car class having two private member variables called tank and speed. write public methods called pumpgas and gofast. the method pumpgas gets an integer for gas that must be pumped. that value needs to be added to tank (no more than 20 gallons). it must return the amount of gas that is purchased ($4 per gallon). the method gofast should increase the speed by 5 each time it is called.write a constructor for the above class that initialized both variables to zero.write a tostring to display both the tank and speed when the car is printed.modify the car class to implement the interface comparable and an interface called carinter having the public methods in carinter.write the main program to create an array of size 5 of type car. create 5 car objects having each location of the array to refer to one of the cars. test the pumpgas, gofast, equals method on the array items. write an enhanced loop to print all the car values (using a tostring written last time).write a generic method to find the minimum of four items. pass int, double, char, string and car objects to test this method.
Answers: 1
question
Computers and Technology, 23.06.2019 14:00
In which job role will you be creating e-papers, newsletters and preiodicals
Answers: 1
question
Computers and Technology, 23.06.2019 14:30
Norder to receive financial aid at his vocational school, mario must fill out the fafsa. the fafsa is a form that must be completed to determine . in order to complete a fafsa, you must submit . the fafsa can students obtain
Answers: 2
question
Computers and Technology, 23.06.2019 20:40
Instruction active describing list features which statements accurately describe the features of word that are used to create lists? check all that apply. the tab key can be used to create a sublist. the enter key can be used to add an item to a list. the numbering feature allows for the use of letters in a list. the numbering feature can change the numbers to bullets in a list. the multilevel list feature provides options for different levels in a list.
Answers: 2
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Chemistry, 23.06.2021 04:30
question
Mathematics, 23.06.2021 04:30
question
Physics, 23.06.2021 04:30
Questions on the website: 13722367