A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

1. If activity E is delayed by 3 days how is the project completion time affected? Why is this the case?

2. If activity F is delayed by 3 days how is the project completion time affected? Why is this the case? Will the critical path change, why or why not?

3. If you want to shorten (crash) the overall time of this project, how do you pick which activity to shorten? What information, if any, do you need?

4. Once you shorten (crash) an activity, do you need to redo the AON, yes or no? Why or why not?

Please answer

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 21.06.2019 15:10
Match the terms in the hlookup syntax with their explanation. a. lookup value b. data table c. row index d. mode 1. name of the table that contains the value 2. specifies if an exact match must be found 3. value to be searched 4. name of the row that contains the value
Answers: 1
question
Computers and Technology, 22.06.2019 14:00
Which database model is best used for data warehouse and data mining
Answers: 3
question
Computers and Technology, 22.06.2019 22:30
Alex’s family members live in different parts of the world. they would like to discuss the wedding plans of one of their distant relatives. however, alex wants all the family members to talk to each other simultaneously so that they can make decisions quickly. which mode of internet communication should they use? a. blog b. email c. wiki d. message board e. instant messaging
Answers: 2
question
Computers and Technology, 23.06.2019 02:30
How to launch an app: steps to be successful? launching an app is a great idea, but it’s not that easy as we supposed to think. the majority of mobile applications don’t generate revenue because companies aren’t ready to be competitive. referring to our experience in successfully building and launching apps we hope to you omit these difficulties. we are going to talk about ideas, marketing, testing your product, its development, distribution and support. you will learn 8 product launch stages to succeed.
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...
Questions
question
Social Studies, 20.08.2019 03:00
question
Chemistry, 20.08.2019 03:00
Questions on the website: 13722363